Electricity transmission and interconnection

Whether the US grid can connect and deliver the generation being built. Pressure from demand growth, capacity growth and retail price; planned retirements are shown as an observed context figure (one vintage, no history to rank) and the interconnection queue has no registered source. Response is the EIA-860M capacity pipeline against trailing additions, with the grid investment capex pulse alongside.

Statusconstrainedthresholds bottleneck_thresholds_v1as of 2026-05-01, computed 2026-09-07 22:36 UTC

Reading

In plain words

generated from the stored numbers, rule bottleneck_thresholds_v1

Pressure is 75 on a 0 to 100 scale (the weighted 75th percentile of its components' own histories) with 3 of 6 components available, 55 percent of the weight, as of 2026-05. Status: constrained. The response signal is 0.94, meaning the 24-month pipeline roughly matches recent additions. Adding capacity takes 7 to 15 years by the cited source, so today's response is read against that horizon.

rules fired: pressure 75.29 >= 75

Is the problem being solved?

Pressure and response

pressure Modeled response Modeled
  • pressure0 to 100, left
  • response ratioratio, right
Electricity transmission and interconnection: pressure and response over time0255075100watch 60constrained 75response threshold 100.511.021976-121984-011991-021998-032005-042012-052019-062026-07PRESSURE (WEIGHTED PERCENTILE)RESPONSE RATIOpressureresponse ratioresponse ratio, 2025-07: 0.94response ratio, 2025-08: 0.89response ratio, 2025-09: 0.91response ratio, 2025-10: 0.91response ratio, 2025-11: 0.89response ratio, 2025-12: 0.94response ratio, 2026-01: 0.94response ratio, 2026-02: 0.93response ratio, 2026-03: 1.02response ratio, 2026-04: 0.96response ratio, 2026-05: 0.93response ratio, 2026-06: 0.93response ratio, 2026-07: 0.94
Pressure: 594 period(s), 1976-12 to 2026-05. Response: 13 period(s), 2025-07 to 2026-07. The two scales are independent; the lines are read against their own thresholds, never against each other.
PressureModeled

75

0 to 100, coverage 55%, 3 of 6 components, as of 2026-05

ResponseModeled

0.94

24-month weighted pipeline / trailing additions, threshold 1, as of 2026-07-01

Pressure components

Percentiles, weights and what is missing

weights sum to 1; missing components count against coverage
ComponentWeightSeries and transformPercentileRawPeriodHistoryStatus
Demand growth
12-month percent change of US net generation (EIA ELETPUS)
0.2us-electricity-net-generation USA
pct_change_12
65.263.09752026-05-01629present
obs 245394, 245395, 245396 ...
Capacity growth gap
12-month percent change of US net summer capacity (EIA ELGBPUS); read directly, higher capacity growth ranks higher because the retirements component carries the loss side
0.2us-electric-net-summer-capacity USA
pct_change_12
87.094.70322026-05-01244present
obs 241165, 241166, 241167 ...
Retail price pressure
12-month percent change of the average retail electricity price (EIA ESTCUUS)
0.15us-electricity-retail-price USA
pct_change_12
72.915.33132026-05-01515present
obs 245921, 245922, 245923 ...
Planned retirements
Capacity scheduled to retire in the next 24 months relative to its own history.
0.2no registered series--------missing
us-planned-generation-retirements is a schedule keyed by retirement month from the latest EIA-860M file (one vintage), so it has no history to rank; the next-24-month total is shown as context
candidates: EIA-860M file history (one next-24-month total per file month)
Interconnection queue
Capacity waiting in interconnection queues and its wait time.
0.15no registered series--------missing
no interconnection queue series is registered
candidates: LBNL Queued Up (annual); ISO/RTO queue reports
Transformer lead time
Delivery lead time for large power transformers.
0.1no registered series--------missing
no transformer lead-time series is registered
candidates: DOE Large Power Transformer Resilience Report (2024); NIAC transformer report (2024)
Planned retirements, next 24 monthsObserved

--

MW, 0 period(s) from --, us-planned-generation-retirements

nameplate MW of operating generators with a reported retirement month in the 24 months after the current month (EIA-860M); observed, not scored (no observations of us-planned-generation-retirements (USA))

Response detail

What the response signal rests on

Metric
us-capacity-response-electricity USA, observation 409127
24-month pipeline, weighted
109,333.015 MW
Trailing 24 months of additions
116,211.3 MW
Computed from
v1.0/860M-2026-07+additions-2026-07
Detail
/capacity

Alongside, not in the score: Grid Investment Pulse capex growth 35.2% as of 2025-12-31 (9 of 10 members, row 2).

Downstream

Systems that depend on it

within 3 hops, centrality_v1
EntityTypeHopsCentrality
Electricity systeminfrastructure_system14.6
Data centerfacility11.75
Semiconductor fabrication plantfacility23.75
AI computetechnology20.75
Economic outputentity20.5
Human health and longevityentity20
High bandwidth memoryproduct32.475
AI acceleratorproduct31.75

Substitutes

Named on the dependency edges

No substitute is named on any stored edge.

Expansion lead time

84 to 180 months

Recommended

New high-voltage transmission line, planning to energisation

Interstate transmission projects from initiation through permitting and construction.

U.S. Department of Energy, Grid Deployment Office, National Transmission Needs Study (2023)

New transmission takes on average around 10 years to complete, with some projects requiring 15 years or more; permits alone average more than four years.

checked 2026-09-07

Evidence

Every number, by id

Bottleneck and Response monitor, model bottleneck_assessment_v1, thresholds bottleneck_thresholds_v1

A record shows two signals and never combines them.

Pressure (modeled): each available component is transformed (12-month percent change, year-over-year growth with the sign reversed for supply, level for shares and lead times), then replaced by its percentile rank (0 to 100) within its own stored history up to that period, ties counted half, after a minimum history. The score is the weighted mean of those ranks over the components present, renormalised. Coverage is the share of declared weight that has data; components without a registered source are declared with their weight, their role and candidate sources, and count against coverage. Weights are a modelling choice and are listed on every record.

Response: the capacity response ratio where a capacity pipeline exists (US electricity: the stage-weighted 24-month EIA-860M pipeline over the trailing 24 months of additions, modeled), otherwise the capital expenditure pulse of the tagged company group (matched-sample trailing-four-quarter capex growth from stored 10-K and 10-Q facts, derived), otherwise null with the reason.

Status comes only from these thresholds:

  • insufficient data: coverage below 0.5, or no pressure score. No label is guessed.
  • below watch: pressure below 60.
  • watch: pressure at or above 60 and below 75.
  • constrained: pressure at or above 75.
  • constrained, response underway: constrained and the response signal clears its threshold (capacity response at or above 1.0, or capex pulse above 10 percent).

Lead time is recommended-class metadata from a small sourced table (src/data/lead-times.ts) and is stored with its citation. Substitutes and downstream systems come from the curated knowledge graph (edges where the record's entity is the dependency; entities within three hops that depend on it, with centrality_v1). Every number on a record traces to stored observation ids, pulse row ids or edge ids in the row's JSON.

History

Assessments stored

As ofPressureCoverageResponseStatusComputed
2026-05-017555%0.94constrained2026-09-07