HUMANITYVECTOR

Objective, 2x by 2040, United States

Double US electricity generation by 2040

What would have to happen for the United States to generate twice as much electricity in 2040 as it does today?

PaceBehind the required pace3.8x recentsnapshot 2026-09-07 22:37 UTC

Current level

4.47Mmillion kilowatthoursDerived

12 months to 2026-05

Sum of the twelve latest monthly observations.

Target level in 2040

8.93Mmillion kilowatthoursDerived

2040

Current level times 2.

Required annual addition

319,064.78million kilowatthours per yearDerived

12 months to 2026-05 to 2040

(target minus current) divided by 14 years. A straight line, not a plan.

Recent pace, trailing 5-year average change

83,082.92million kilowatthours per yearDerived

12 months to 2021-05 to 12 months to 2026-05

(12 months to 2026-05 level minus 12 months to 2021-05 level) divided by 5.

Forecast pace, Forecast Lab 5-year horizon

unavailableModeled

The Forecast Lab forecasts this series monthly at 1 to 12 month horizons; no annual trajectory is stored.

Required pace minus recent pace

235,981.86million kilowatthours per yearDerived

Positive means the objective needs a faster pace than the trailing five years delivered.

Required pace minus forecast pace

unavailableModeled

The Forecast Lab forecasts this series monthly at 1 to 12 month horizons; no annual trajectory is stored.

Target metric US electricity net generation, entity Electricity system, base year 2026, 14 years to go, forecast us-electricity-net-generation 5-year.

Same engine, same stored rows, no AI

Explore a different target

Backward walk over requires_input, depends_on and constrains edges, depth 4, 5 constraints

Dependency tree

Objective on the left, what it needs to the right

Double US electricity generation by 2040: dependency walk from electricity-systemelectricity-system requires input power-grid: Established relationpower-grid requires input power-transformer: Established relationpower-transformer requires input copper: Established relationpower-transformer requires input aluminum: Established relationpower-transformer requires input electrical-steel: Established relationElectricity systemTransmission anddistribution gridPower transformerRefined copperPrimary aluminumGrain-orientedelectrical steel
  • Candidate
  • Hypothesized
  • Mechanism supported
  • Causally supported
  • Established relation
depth 1 Transmission and distribution gridinfrastructure system84 to 180 months

Established relationrequires inputstrength 1confidence 0.99relationshipwhy Transmission and distribution grid

Electricity is generated in one place and used in another. Delivering it to homes and industry physically requires transmission lines, substations and distribution networks; access statistics count connections to that network.

Input coefficient
hypothesized dependence, no stored coefficient
Bottleneck status
no bottleneck row stored
Lead time
84 to 180 months (Interstate transmission projects from initiation through permitting and construction.) U.S. Department of Energy, Grid Deployment Office Recommended

New transmission takes on average around 10 years to complete, with some projects requiring 15 years or more; permits alone average more than four years.

Substitutes
none stored on this edge
Response under way
US generation pipeline, stage-weighted, expected online within 24 months: 109,333.02 MW (2026-07-01) Modeled

291,138 MW of planned generators in the EIA-860M 2026-07 inventory before stage weights; 116,211 MW came online in the trailing 24 months (observed).

Also needed by
Data center
depth 2 Power transformerproduct24 to 60 months

Established relationrequires inputstrength 1confidence 0.99relationshipwhy Power transformer

Power is transmitted at high voltage to limit losses and stepped down for distribution. Every generator connection, substation and distribution feeder passes through transformers, so grid expansion and interconnection queues move with transformer supply and lead times.

Input coefficient
hypothesized dependence, no stored coefficient
Bottleneck status
no bottleneck row stored
Lead time
24 to 60 months (Delivery of a large power transformer from order, at current order books; a new transformer plant takes longer.) U.S. Department of Energy Recommended

Lead times for large power transformers can reach as much as 60 months; the NIAC report of June 2024 puts current lead times at roughly two to four years.

Substitutes
none stored on this edge
Response under way
Grid Investment Pulse: 0.3521 fraction (2025-12-31) Derived

9 companies contributed to the stored pulse.

Also needed by
no other stored dependent
depth 3 Refined coppercommodity120 to 240 monthsbottleneck row

Established relationrequires inputstrength 0.8confidence 0.95relationshipwhy Refined copper

Transformer windings are conductors carrying the full load current. Copper is the standard winding material for its conductivity and mechanical strength; aluminum windings are used in many distribution transformers at a larger cross-section.

Input coefficient
hypothesized dependence, no stored coefficient
Bottleneck status
Copper: insufficient data, severity 85.48 (2026-07-01) Recommended
Lead time
120 to 240 months (expansion lead time, bottlenecks table) Humanity Vector Recommended
Substitutes
  • Primary aluminum: Aluminum windings, larger cross-section for the same current; common in distribution transformers.
Response under way
Heavy Industry Pulse: no value stored Derived

No pulse stored yet (corporate.recompute_pulses has not run, or no facts are stored).

depth 3 Primary aluminumcommodity

Established relationrequires inputstrength 0.4confidence 0.9relationshipwhy Primary aluminum

Aluminum is the alternative winding conductor and is used in tank and structural parts; it is lighter and cheaper per unit of conductance but needs more volume.

Input coefficient
hypothesized dependence, no stored coefficient
Bottleneck status
no bottleneck row stored
Lead time
no cited lead time
Substitutes
Response under way
Heavy Industry Pulse: no value stored Derived

No pulse stored yet (corporate.recompute_pulses has not run, or no facts are stored).

Also needed by
no other stored dependent
depth 3 Grain-oriented electrical steelmaterial

Established relationrequires inputstrength 0.9confidence 0.95relationshipwhy Grain-oriented electrical steel

Transformer cores are stacked laminations of grain-oriented electrical steel chosen for low core loss. Amorphous alloy cores are a partial alternative in distribution units; there is no drop-in core material for large power transformers.

Input coefficient
hypothesized dependence, no stored coefficient
Bottleneck status
no bottleneck row stored
Lead time
no cited lead time
Substitutes
none stored on this edge
Response under way
Heavy Industry Pulse: no value stored Derived

No pulse stored yet (corporate.recompute_pulses has not run, or no facts are stored).

Also needed by
no other stored dependent

Arithmetic on stored values; ranges follow the inputs

Required additions

QuantityValueClassBasis
Required annual addition

(target minus current) divided by 14 years. A straight line, not a plan.

319,064.78 million kilowatthours per yearDerivedobs:245385 obs:245386 obs:245387 obs:245388 obs:245389 obs:245390 +6
Capacity added per year if all utility solar

Required annual generation divided by 8760 hours and a capacity factor of 0.2 to 0.3 (cited).

121.41 to 182.11 GW per yearModeledcoef:cf_solar_utility obs:245385 obs:245386 obs:245387 obs:245388 obs:245389 +8
Copper needed per year if all utility solar

Capacity times 2800 to 2900 kg of copper per MW (hypothesized, read from a chart).

339.95 to 528.13 thousand metric tons per yearModeledcoef:cf_solar_utility coef:copper_per_mw_solar obs:245385 obs:245386 obs:245387 obs:245388 +10
Capacity added per year if all onshore wind

Required annual generation divided by 8760 hours and a capacity factor of 0.3 to 0.55 (cited).

66.22 to 121.41 GW per yearModeledcoef:cf_wind_onshore obs:245385 obs:245386 obs:245387 obs:245388 obs:245389 +8
Copper needed per year if all onshore wind

Capacity times 2900 to 3000 kg of copper per MW (hypothesized, read from a chart).

192.05 to 364.23 thousand metric tons per yearModeledcoef:cf_wind_onshore coef:copper_per_mw_wind_onshore obs:245385 obs:245386 obs:245387 obs:245388 +10
Capacity added per year if all gas combined cycle

Required annual generation divided by 8760 hours and a capacity factor of 0.3 to 0.9 (cited).

40.47 to 121.41 GW per yearModeledcoef:cf_gas_combined_cycle obs:245385 obs:245386 obs:245387 obs:245388 obs:245389 +8
Copper needed per year if all gas combined cycle

Capacity times 1100 to 1200 kg of copper per MW (hypothesized, read from a chart).

44.52 to 145.69 thousand metric tons per yearModeledcoef:cf_gas_combined_cycle coef:copper_per_mw_gas obs:245385 obs:245386 obs:245387 obs:245388 +10
Capacity added per year if all nuclear

Required annual generation divided by 8760 hours and a capacity factor of 0.89 to 0.92 (cited).

39.59 to 40.92 GW per yearModeledcoef:cf_nuclear obs:245385 obs:245386 obs:245387 obs:245388 obs:245389 +8
Copper needed per year if all nuclear

Capacity times 1400 to 1500 kg of copper per MW (hypothesized, read from a chart).

55.43 to 61.39 thousand metric tons per yearModeledcoef:cf_nuclear coef:copper_per_mw_nuclear obs:245385 obs:245386 obs:245387 obs:245388 +10
Transmission and distribution grid needed per yearnot estimatedhypothesized dependencerel:5148efdc-e97b-4641-a51f-cf6e681c89d5
Power transformer needed per yearnot estimatedhypothesized dependencerel:0f9233ff-917a-41b9-bf03-ffb05c829ced
Refined copper needed per yearnot estimatedhypothesized dependencerel:57478abe-2355-4de1-8b4d-be19c58b7045
Primary aluminum needed per yearnot estimatedhypothesized dependencerel:aa5d07e3-221c-4748-b5bc-d3b871fcb961
Grain-oriented electrical steel needed per yearnot estimatedhypothesized dependencerel:361814d4-9451-4107-b575-92a3073b6956

Capacity pipeline and corporate pulses that map to the walk

Current pipeline and responses

Only where a coefficient and a sourced unit cost both exist

Capital

  • Capital per year if all utility solar

    139.62 to 291.38billion USD (2025 dollars) per yearModeled

    Capacity times 1,150 to 1,600 USD per kW. Generation plant only: no transmission, storage, land or financing cost. Unit cost 1,150 to 1,600 USD per kW, Lazard.

  • Capital per year if all onshore wind

    125.82 to 279.24billion USD (2025 dollars) per yearModeled

    Capacity times 1,900 to 2,300 USD per kW. Generation plant only: no transmission, storage, land or financing cost. Unit cost 1,900 to 2,300 USD per kW, Lazard.

  • Capital per year if all gas combined cycle

    48.56 to 194.26billion USD (2025 dollars) per yearModeled

    Capacity times 1,200 to 1,600 USD per kW. Generation plant only: no transmission, storage, land or financing cost. Unit cost 1,200 to 1,600 USD per kW, Lazard.

  • Capital per year if all nuclear

    357.1 to 606.5billion USD (2025 dollars) per yearModeled

    Capacity times 9,020 to 14,820 USD per kW. Generation plant only: no transmission, storage, land or financing cost. Unit cost 9,020 to 14,820 USD per kW, Lazard.

Downstream systems that compete for the same inputs; the engine does not rank them

Tradeoffs

What is unavailable, hypothesized or modeled

Uncertainty

  • Forecast pace: The Forecast Lab forecasts this series monthly at 1 to 12 month horizons; no annual trajectory is stored.
  • Transmission and distribution grid: hypothesized dependence, no stored coefficient, so no quantity of it is computed.
  • Power transformer: hypothesized dependence, no stored coefficient, so no quantity of it is computed.
  • Refined copper: hypothesized dependence, no stored coefficient, so no quantity of it is computed.
  • Primary aluminum: hypothesized dependence, no stored coefficient, so no quantity of it is computed.
  • Grain-oriented electrical steel: hypothesized dependence, no stored coefficient, so no quantity of it is computed.
  • Capital not estimated for Transmission and distribution grid, Power transformer, Refined copper, Primary aluminum, Grain-oriented electrical steel: no coefficient plus unit cost pair is stored for them.

Stated, versioned, and shown before the numbers are trusted

Assumptions

  • Base year 2026: the required pace divides the whole gap evenly over 14 years.
  • The constraint walk follows requires_input, depends_on and constrains edges to depth 4; an entity reached twice is listed once at its shortest depth. Anything the curated graph does not store is not listed.
  • Lead times are order-to-delivery or discovery-to-production ranges from the cited documents; they do not include financing or permitting unless the source says so.
  • Each capacity scenario assumes every added kilowatt-hour comes from one technology; real additions mix technologies, so the four rows bound the range rather than predict it.
  • Capacity factors and capital costs are the Lazard LCOE+ v18 (June 2025) assumption ranges for new US builds, not observed fleet averages.

AI-written from the numbers above, grok-4.3, prompt 1.0.0, validated against the packet

Narrative

The objective asks for [q:target] in 2040 from [q:current]. Required annual addition is [q:required]. Recent pace is [q:recent] so [q:gap_recent] is positive. Forecast pace is unavailable.

Deepest lead time first: [rel:57478abe-2355-4de1-8b4d-be19c58b7045] 120 to 240 months for Refined copper (insufficient data), substitutes Primary aluminum, also needed by Residential construction. Next [rel:5148efdc-e97b-4641-a51f-cf6e681c89d5] 84 to 180 months for Transmission and distribution grid, also needed by Data center. Then [rel:0f9233ff-917a-41b9-bf03-ffb05c829ced] 24 to 60 months for Power transformer. [rel:361814d4-9451-4107-b575-92a3073b6956] for Grain-oriented electrical steel. [rel:aa5d07e3-221c-4748-b5bc-d3b871fcb961] for Primary aluminum, substitutes Refined copper. Electricity system also needed by Semiconductor fabrication plant.

[q:forecast] and [q:gap_forecast] are unavailable because no annual trajectory is stored. [q:addition:0] through [q:capital:3] are modeled with ranges from cited capacity factors and hypothesized copper per MW read from a chart. [q:response:2] is unavailable because no pulse stored yet.

ai run 34d3ea69-3b0c-433c-aebb-ef86651f3760, 2026-09-07 22:37 UTC. The model restates computed values and cites packet ids; it adds no figure and makes no recommendation.

Version objectives_v1, as of 2026-09-07. 48 stored ids cited. The objective was selected by a reader; the engine evaluates it and shows what competes with it, and does not decide that it should be pursued.